|
Exhaust Systems Repair, Building 503 WRAIR,
WRAMC, Forest Glen Silver Spring, MD
|
| Type of Contract: Firm fixed price |
|
| Date of Award: September
2004 |
Dat of Completion: April 26, 2006 |
| Award Amount: $
1.4 Million |
Final Amount: $ 1.6
Million |
| Description of Project: HVAC duct modification |
 |
| |
 |
EEC identified a design flaw prior to
construction |
 |
Despite a 17 months Government delay |
 |
EEC did not seek delay and impact costs |
 |
Bio-decontamination of six BSL 3 |
 |
Labortries and thousands of feet of ductwork |
|
|
The project involved the bio-decontamination of six Bio
Safety Level 3 laboratories and over two thousand linear feet of associated
ductwork that was 40 inches in diameter using Vaporized Hydrogen Peroxide
(VHP), the replacement of supply and return dampers and a modification to the
ductwork system. It also involved the installation of a HEPA Filter Bank.
The project was unique because of the large volume of ductwork to be
decontaminated and also prior to this project all decontamination
performed had been confined between the laboratories and the final HEPA
filters. EEC had to remove the HEPA filters under negative pressure and make the
top of the flue duct airtight to contain the VHP during the decontamination
process.
Another challenge was the installation of the filter bank.
Custom insulated wall panels had to be taken down along one wall that was over
eighty feet high to create access for the filter bank. Finally, the schedule was
critical and had to be met. All work associated with the first three lab suites
was completed in 30 days and the final set completed in another 30 days with two
modifications of added work. The project was completed on
schedule.
EEC's commitment to our valued clients were exhibited in waving
all extended overhead damages that were incurred by EEC as a result of the 17
month contract delay due to the client's engineers design
specifications.
|
| Next |